Reviving LRT project makes sense, but Japan’s re-entry is tied to pre-conditions    

Posted by
Check your BMI

By P.K.Balachandran/Daily Mirror

Colombo May 9: Reviving the Colombo Light Rail Transit (LRT), abruptly suspended in 2020, makes eminent sense from the transport point of  view. But collaborator Japan’s re-entry into the project is tied to tough pre-conditions set by Tokyo, it is reliably learned.

Japanese sources said that Sri Lanka will have to ensure that foreign investments are safeguarded; the country’s financial condition is stable; the international debt restructuring process is well and truly underway and China’s compliance with any consensus is ensured. This is indeed a tall order putting Sri Lanka in a tough spot.

However, it is in Sri Lanka’s interest to pursue the LRT project and find a willing international financial partner.

Sri Lanka’s Ministry of Urban Development has said that it has called for a report from an expert committee for the revival of the US$ 2.2 billion Colombo Light Rail Transit (LRT) Project that was abruptly abandoned during the Gotabaya Rajapaksa Presidency.

A revived LRT project promises to be profitable, assuring a 20% return on investment, according to a transport expert from Moratuwa University. The re-entry of Japan into the project is a sine qua non for the project’s success, but Japan is wary because of its bitter experience with the project in the recent past.   

In 2019, the Japan International Cooperation Agency (JAICA) had agreed to grant a soft loan of US$ 1.8 billion with an annual interest of 0.1% to be repaid over 40-years with a 12-year grace period.

The LRT project was to be a solution for traffic congestion in Colombo and its suburbs especially during peak hours. Phase I of the LRT project was to cover 16.7  km on an elevated track from Malabe to Colombo Fort with 16 stations covering the distance in 32 minutes.

But influenced by a leading transport economist, the Gotabaya regime on September 21, 2020, ordered the immediate termination of the project without giving Japan advance notice or consulting it. In the then government’s view US$ 2.2 billion was too costly for the project’s “limited use”.

But apart from putting off Japan, a time-tested friend of Sri Lanka’s, the cancellation of the project had cost the country Rs. 5.978 billion, according to the National Audit Office. The cancellation also resulted in a waste of Rs. 10.6 billion because multiple parties had spent this amount already.

The Urban Development Authority (UDA) will now call for expressions of interest (EOIs) from interested international firms or joint venture companies to build the necessary infrastructure and implement the project subject to the Cabinet of Ministers’ approval.

But the million-dollar question is: Will Japan re-enter the project swallowing the earlier insult? The Japanese Ambassador to Sri Lanka Hideaki Mizukoshi was quoted in the media in March as saying: “No decision has yet been made. But it all depends on how the reforms of the Sri Lankan government go and whether Sri Lanka can regain the trust from the Japanese government and the business community.”

Speaking at a breakfast forum organized by the Ceylon Motor Traders Association in Colombo, he said: “When those conditions are met, I think it will be considered.”

20% Return on Investment  

Dimantha de Silva, Senior Lecturer in the Transportation Engineering Division of Moratuwa University, told this correspondent after the cancellation that the project was worthwhile both from the point of view of present and future transport needs of Colombo and the return on investment.

The project would have assured a 20% return on investment in addition to providing a sustainable solution to traffic congestion to a corridor that has the highest vehicle growth and biggest traffic jams at the moment, de Silva said.

“The elevated track would have taken a good chunk of the traffic during peak hours and would have had Rs. 38 billion of economic benefit per year in terms of travel time savings and fuel cost savings,” he added.

Going at 80 km per hour, the train would have carried 800 passengers per train when first operated in 2025 and 1200 passengers per train when operating in 2035, de Silva said.

The first installment of the repayment was to be given in 2030 after six years of operation and obtaining economic benefits. The last installment was expected to be given in 2058. One of the conditions was that 30% of the products used should be of Japanese origin.

De Silva said that if the cost per kilometer appeared to be high, it was because the distance was short (just 16.7 km), adding that the per km cost usually optimizes for around 30 km distance since fixed cost components such as system costs for electrical and mechanical systems, communication and signal systems together with rolling stock and maintenance yard are fixed for a length of around 30 km.

However, when the line is extended from Malabe to Kaduwela and to Kottawa (via Athurugiriya), as per the Master Plan, making it around 30kms, the per kilometer cost will come down to around US$ 50-55 million per km based on the engineering estimates completed recently, de Silva said.

As for the argument that the railways are not being used by Sri Lankans, his counter was that people use the railway heavily when railways are available.

According to the feasibility study, the estimated passenger trip demand for the Malabe-Fort line in 2025 is 363,000 with over 14,300 passengers per hour being transported in peak hour direction. The estimated passenger trip demand in 2035 is 498,000 with 19,800 passengers per hour in peak direction, where travel time from Malabe to Fort will be 32 minutes and from Fort to Sethsiripaya will be 18 minutes.

While the space under the elevated track can be used for commercial purposes, the elevated track obviates the need for level crossings, which if closed frequently will disrupt the smooth flow of road traffic, de Silva said.

With thousands taking the LRT, congestion on the roads will be reduced and vehicles can move faster, cutting down on travel time and fuel use, he added.

Million Dollar Question

But the million-dollar question is: Will Japan re-enter the project swallowing the earlier insult? The Japanese Ambassador to Sri Lanka Hideaki Mizukoshi was quoted in the media in March as saying: “No decision has yet been made. But it all depends on how the reforms of the Sri Lankan government go and whether Sri Lanka can regain the trust of the Japanese government and the business community.”

Speaking at a breakfast forum organized by the Ceylon Motor Traders Association in Colombo, he said: “When those conditions are met, I think it will be considered.”

Systemic Challenges to FDI

About the poor investment climate in Sri Lanka, here is an assessment of the US State Department for 2021: The report says: “Sri Lanka is a challenging place to do business, with high transaction costs aggravated by an unpredictable economic policy environment, inefficient delivery of government services, and opaque government procurement practices.  Investors noted concerns over the potential for contract repudiation, cronyism, and de facto or de jure expropriation.”

“Public sector corruption is a significant challenge for U.S. firms operating in Sri Lanka and a constraint on foreign investment.”

“While the country generally has adequate laws and regulations to combat corruption, enforcement is weak, inconsistent, and selective.  US stakeholders and potential investors expressed particular concern about corruption in large infrastructure projects and in government procurement.”

“The government pledged to address these issues, but the COVID-19 response remains its primary concern.  Historically, the main political parties do not pursue corruption cases against each other after gaining or losing political positions.”

In February this year, Nikkei Asia reported that after the Mitsubishi Corporation wound up its operations in Sri Lanka, another Japanese company Taisei Corp, too, decided to pull out as Sri Lanka’s economic crisis made doing business difficult.

In March 2020, Taisei won a contract worth US$ 462 million for the construction of a four-story passenger terminal building, an elevated bridge and more for the second phase of the expansion of the Bandaranaike International Airport at Colombo. As the economic turmoil deepened, and loan repayments stopped and JICA stopped lending for the project.

Japan was to participate in the building of the Eastern Container Terminal in Colombo port along with India, but the Rajapaksa government called off the international involvement in the project following a short agitation by workers.

END